Project Quality Management- Sample Questions



Question - 1

Comparing your project with actual or planned project practices to generate ideas for improvement is called:

A. Benchmarking

B. Benefit/Cost analysis

C. Quality audits

D. Process Analysis


A is the correct answer. Comparing your project with actual or planned project practices to generate ideas for improvement is called Benchmarking.


Question - 2

Who is primarily responsible for creating design and test specifications?

A. Quality Control

B. Engineering

C. Support

D. Management


B is the correct answer. Engineering is primarily responsible for creating design and test specifications.


Question - 3

Conformance to specifications document is a description of:

A. Quality

B. Scope

C. Integration

D. None of the above


A is the correct answer. Quality on a project means that you are conforming to a standard that is set before you start the project.


Question - 4

Who is responsible for the quality of the project deliverables?

A. Project team

B. Project manager

C. Stakeholders

D. Customer


A is the correct answer. The project team is responsible for the quality of the project deliverables.


Question - 5

You are the project manager for a big size project and quality is top priority for this project. You have devoted so much of the project time for planning. Why?

A. It is mandatory to allocate much time to planning for a project of this size and with this amount of quality

B. Quality is planned into the project and the planning requires time

C. Quality audits are part of the planning time

D. All of the above


B is the correct answer. Quality is planned into the project and the planning requires time.


Question - 6

You are the project manager and you meet with your project team to ensure the project is completed with no deviations from the project requirements.This is part of?

A. Control Quality

B. Manage Quality

C. Plan Quality Management

D. All of the above


C is the correct answer. Plan Quality Management should be completed prior to the work beginning and revisited as needed. Plan Quality Management: Identifying the quality standards that are relevant to the project and determining how to meet them.


Question - 7

You are managing a project. This project must satisfy industry standards in order to be accepted by the customer. You and your team have studied the requirements and have created a plan to implement the deliverables with the level of quality. This process is called ________.

A. Control Quality

B. Manage Quality

C. Plan Quality Management

D. All of the above


C is the correct answer. Plan Quality Management: Identifying the quality standards that are relevant to the project and determining how to meet them.